The proposed Heartland Transmission Project involved the construction of a high voltage transmission line which will connect the Heartland region (northeast of Fort Saskatchewan) to existing transmission facilities either west of Edmonton or in southern Edmonton. AltaLink and EPCOR, the Heartland Project Team, are working together on the project’s development.
Truescape supported the project by preparing both TrueView™ photo simulations, a video animation and also provided Expert Witness testimony before the Alberta Utilities Commission.
Upon construction of the project in 2014, we carried out some analysis to determine the accuracy of the TrueView™ visualizations that were presented to the Alberta Utilities Commission hearing in 2011.
The findings clearly confirm the accuracy of the TrueView™ photo simulations and validate the methodology used to build them.